|
University of Tropical
Agriculture Foundation -UTA- |
|
| Back to Recent Developments |
Biodigesters |
|||||
| A Biodigester in Bricks
and Concrete using the principles of the Plastic Biodigester:
A legitimate criticism of the plastic biodigester (using tubular polethylene film) in a village situation is that it is easily broken by scavenging animals, which are not always easy to control. Using stronger materials, such as bricks and cement, for the digestion chamber is a feature of the Chinese and Indian models. However, these models are expensive (at least USD250.00 for a system with 6 m³ of liquid volume). In Cambodia and Vietnam, and in countries with similar low per capita income, the cost must be kept low if the technology is to have an impact at the level of the average household. The “hybrid” biodigester, developed first in Vietnam by VACVINA
(Claude Potvin 2000, personal communication), and now being adapted to
conditions in Cambodia, appears to offer the most interesting line of
improvement. The “hybrid” (combination of Indian / Chinese and plastic plug-flow designs) biodigester system uses a chamber made of bricks and cement (or “shuttered” concrete) to replace the plastic bag; the rest of the system is the same as for the “plastic’ model. The use of the polyethylene reservoir (Photo 1) enables the system to operate at low pressure, thus avoiding the more complicated (and expensive) construction used in the “dual-compartment” “Chinese” model or the "Indian" floating dome system, which in turn leads to reduced costs. For the farm with more than 6 - 8 pigs there is the opportunity to use the roof of the biodigester as the floor of the pig pen (Photos 2-14). Preliminary estimates of the costs of materials for a biodigester 6m long and 1m² section (liquid volume about 5 m³) are of the order of USD60.00, excluding the labour. The
simple construction of the “hybrid”
biodigester facilitates construction and the skills to do this are
available at household level in almost all villages, thus the labour can
in most cases be provided by the family members. |
||||||
|
|
||||||
|
Photo 1. Biogas reservoir made from tubular polyethylene film |
||||||
|
The principle of the "hybrid" biodigester is that "biogas" is lighter (has lower density) than air, thus it will migrate (rise) to the highest points in the biodigester system. Thus the digestion chamber does not have to made to the same "exacting" specification as in the "Chinese" dual compartment model where pressures may be as high as 1m of water gauge. The pressure in the "plastic" and "hybrid" biodigester is no more 1-2 cm water gauge. The digestion chamber is based on the same "trench" system as the plastic biodigester but is lined with bricks and coated with cement, with a roof that is "cast" in situ (Photo 3) or formed from slabs that are cast separately (Photo 4) and then laid on top of the chamber (Photo 4). |
||||||
| The "hybrid" biodigester combined with a pig pen at the NGO "SCALE" in Cambodia (Pen Rotha and Khang Ming) | ||||||
![]() |
![]() |
|||||
| Photo 2.General view of the pig pen | Photo 3. The biodigester in the central corridor of the pig pen | |||||
|
|
|||||
| Photo 4. The pit to collect the effluent | Photo 5. Casting the slab which forms the roof of the biodigester. | |||||
|
|
|||||
|
Photo 6. The channel around the pens which conveys the manure and washings into the biodigester |
||||||
|
|
|||||
|
Photo 7. The entrance to the syphon which will convey the manure and washings into the biodigester. Additional manure (eg: from cattle) can be added at this point |
||||||
|
|
|||||
|
Photo 8. The pipe from the syphon that exits into the biodigester |
Photo 9. The "man-hole" that provides an entrance into the biodigester, together with the cover |
|||||
|
|
|||||
|
Photo 10. The cover in place over the "man-hole". A seal with clay and water will be put around the edges. |
Photo 11. The passage giving entrance to the pens and which is also the roof of the biodigester. The"man-hole" is in the foreground. |
|||||
| <More
photos will be added as the construction develops.>
|
||||||
|
Integrated pen and biodigester for lactating sows at UTA (Dr Thomas R Preston, Lylian
Rodriguez and San Thy)
The diagrams show the general layout of the 8 pens for the sows with a creep area for the piglets (Figures 1 ands 2). The biodigester chamber is 1.2 m wide and 1m deep. At the two points (*) where four pens coincide, immediately above the centre line of the biodigester, a siphon is fitted through which the washings enter the biodigester chamber (Figure 3). A square hole ([ ]), fitted with a gas-tight cover, is situated in the roof of the digestion chamber, in the part that is outside the pig pen (Figure 1). This provides access into the digestion chamber for cleaning or other maintenance tasks. The cover sits inside a water seal to prevent leakage of the biogas (Figure 4). |
||||||
Figure 1: Floor plan of the 8 pens (concrete surface with 7% slope for the sow pen; and earth floor in the creep area for the piglets) and the biodigester chamber |
||||||
|
Figure 2: Section of the building showing arrangement of the sow pens over the biodigester
|
||||||
Figure 3: Vertical section of the biodigester chamber showing the siphon through which the washings from the pig pen (faeces, urine and water) enter the digestion chamber. The siphon serves as water trap preventing the escape of the gas |
Figure 4: Details of the entrance to the digestion chamber, showing the cover (in red), retaining shoulder (green) and water seal (blue), the latter made from a mixture of clay and water |
|||||
|
|
||||||
|
|
|||||
| Photo 6: Digging the trench for the digestion chamber | Photo 7: Lining the walls of the digestion chamber with bricks | |||||
|
|
|||||
| Photo 8: Preparing the reinforcing for the "slabs" that will form the roof of the digestion chamber | ||||||
|
|
|
|||||
| Photo 9: Making the concrete slabs that will form the roof of the digestion chamber. A hole is left in the centre of one of the slabs where the manure inlet "syphon" will be fitted. | ||||||
|
|
|||||
| Photo 10: Close-up view of the hole for the inlet "syphon" |
Photo 11: Fitting the concrete tube for the outlet of the
digestion chamber
|
|||||
|
|
|||||
|
Photo 12: The outlet tube viewed from inside the digestion
chamber.
|
Photo 13: The outlet tube viewed from outside the digestion chamber, where the effluent will be collected | |||||
|
|
|||||
| Photo 14: The completed exit chamber which will receive the effluent | ||||||
|
|
|
|||||
| Photo 15: Putting the concrete slabs to form the roof of the digestion chamber | Photo 16: The inlet for the manure is situated at the midpoint of the slab where the four pens will coincide (see Figure 1) | |||||
|
|
|
|||||
| Photo 17: The other slabs are laid to form the complete roof of the digestion chamber | ||||||
|
|
|
|||||
| Photo 18: The preparation of the siphon made from sections of PVC tubing | ||||||
Photo 19: The arms of the siphon are cut so that the exit of the siphon is 15cm below the roof of the digestion chamber |
Photo 20: The siphon ready to be installed |
|||||
Photo 21: The siphon installed in the roof of the digestion chamber |
Photo 22: The siphon located in the point where 4 pens coincide. The floors of these 4 pens will be made with 7% slope towards the siphon |
|||||
Photo 22: The part of the digestion chamber outside the pig pen where the entrance hatch will be placed, |
Photo 23: The outlet for the biogas |
|||||
|
|
|||||
| Photo 24: The roof structure is put in place (the entrance hatch is in the foreground) | Photo 25: The roof structure (the exit pit for the effluent is in the foreground) | |||||
|
|
||||||
| Photo 26: The cover for the "man-hole" that will provide access to the digestion chamber | ||||||
|
|
|
|||||
| Photo 27: The "man-hole" providing access to the digestion chamber | ||||||
|
|
|||||
| Photo 28: The finished "man-hole | Photo 29: The floor of the pigpen has a 7% slope leading to the "siphon" in the corner | |||||
|
|
|
|||||
| Photo 30: The biogas is stored in a tubular plastic bag suspended in the roof space above the pens. The"man-hole" cover with the water seal is in the left foreground. | Photo 31: The manure entering the biodigester in the far corner of the pen and the gas being collected in the reservoir in the roof | |||||
|
Conclusions The construction has been successful in ensuring efficient and rapid drainage of manure into the biodigester. The failure was in not making gas-tight the join between the walls and the roof sections. Thus gas did not accumulate in the reservoir bag connected to the gas outlet. As of writing this note (2 January 2001), these joins in the roof space have been plastered more carefully and a suspension of cement in water was "brushed" over all the surfaces containing the gas space. Pigs have been re-introduced into the pens and we await the results. 12 February 2001 We thought the problem had been solved and that the "plastering" and "brushing" (with a cement-water suspension) of the walls and roof of the gas space of the biodigester had been successful. The system began to produce gas (Photos 30 and 31). |
||||||
![]() |
![]() |
|||||
|
Photo 32: The PVC pipe attached to the syphons under the pig pen |
Photo 33: The PVC pipe is linked to the polyethylene tubular digester | |||||
|
1 March 2001 |
||||||
| For further
information, questions or comments please contact: |
||||||
| Dr Thomas R Preston | trpreston@uta.edu.kh | |||||
| SCALE (Mr Pen Rotha or Mr Kang Minh) | 012845050@mobitel.com.kh | in Khymer | ||||
| Lylian Rodriguez J | lylianr@yahoo.com | |||||
| San Thy | santhy@uta.edu.kh | in Khymer | ||||